This is where Maxcon and the construction team are at on Penny Place Apartments as at the end of September 2020.
- Level 21 windows commenced
- Level 21 balustrade & A/C boxes installed
- Level 20 plaster now complete
- Level 20 services (rough-in) now complete
- Joinery installed to Level 18
- Level 15 stone installed
- Level 13 tiling commenced
- Services second fix complete to Level 14
- Splashbacks installed to Level 14
- Bin chutes installed to Level 14
- FFE installed to Level 13
Completion is expected early Q2 2021.