Construction Update for November 2019

The Contractor (Maxcon) commenced works on site in the first week of October and has diligently been undertaking in-ground works.

Piling works also commenced in mid-November. As a result of hard work Maxcon have been able to complete the piling works in a two-week period.

Works for the raft slabs and pad footings are currently being undertaken and the preparation of the crane base is also in progress and expected to be complete over the coming days. Check out our time-lapse video for November below.

Our official Ground-Breaking Ceremony was undertaken on the 20 November with the Hon Stephan Knoll - SA Minister for Planning and guests in attendance on what was an extremely hot day +40 degrees.