Construction Update for December 2019

Our Contractor (Maxcon) continued works during December. The buildings footprint was completed during this period with all substructure and ground floor slab works poured (visible in the site image).

Ground floor columns framing and reinforcing has commenced and preparations made to receive the first precast panels on site in January.

Concrete pits for the tower crane and Alimak were completed for installation in January and February respectively.

In accordance with South Australia Police requests and as agreed by the relevant authorities the Contractor has taken control of a portion of Nelson Street. Pedestrian and bicycle access is available via Penny Place and the Kodo laneway through to Angas Street.